LAWA and the Part 161 Consulting Team have identified the following major project milestones. Additional detail will be added as the project progresses.
| |
January 2007 |
|
Confirm operations and fleet mix operating at the airport and in the U.S. Confirm aircraft decibel levels with FAA, aircraft manufacturer databases and the operators |
| June 2007 |
Refine draft ordinance |
| September 2007 |
Conduct operator and tenant surveys to identify possible operations and economic impacts of proposed phaseout |
| September 2007 |
Establish baseline and forecast operating and noise conditions if restrictions were not implemented |
| December 2007 |
Analyze noise benefits and economic costs of proposed phaseout and alternatives |
| September 2008 |
Environmental review process including meeting CEQA requirements |
| December 2008 |
Prepare draft documentation for Board consideration and additional instructions |