LAWA and the Part 161 Consulting Team have identified the following major project milestones. Additional detail will be added as the project progresses.
| |
March 2009 |
|
Complete required analyses of the alternative restrictions under consideration |
| April 2009 |
Present results of analyses of alternative restrictions to Board of Airport Commissioners |
| May 2009 |
Complete draft of required Part 161 documentation of the proposed restriction(s) approved by Board of Airport Commissioners |
| June 2009 |
Prepare and distribute Notice of the proposed restriction(s) approved by Board of Airport Commissioners |
| September 2009 |
Prepare final documentation and applications for submittal to the FAA |
| October 2009 |
Provide final text of proposed restrictions to Board of Airport Commissioners |
| December 2009 |
Complete Public Outreach Program |
| |
|
| |
|
The schedule for the parallel process related to the grandfathered phaseout of noisier aircraft is presented here.