LAWA and the Part 161 Consulting Team have identified the following major project milestones. Additional detail will be added as the project progresses.
|
2nd Quarter 2009 |
|
Complete required analyses of the alternative restrictions under consideration |
| 3rd Quarter 2009 |
Present results of analyses of alternative restrictions to Board of Airport Commissioners |
| 3rd Quarter 2009 |
Complete draft of required Part 161 documentation and final text of the proposed restriction(s) approved by Board of Airport Commissioners |
| 4th Quarter 2009 |
Prepare and distribute notice of the proposed restriction(s) approved by Board of Airport Commissioners |
| 4th Quarter 2009 |
Prepare final documentation and applications for submittal to the FAA |
| 2nd Quarter 2010 |
Complete Public Outreach Program |
|
The schedule for the parallel process related to the grandfathered phaseout of noisier aircraft is presented here.
|